“Miracle” of the electricity industry: 500KV line 3 completed in 7 months
Event News, News

“Miracle” of the electricity industry: 500KV line 3 completed in 7 months

Previously, the 500kV line 3 project from Vung Ang to Pleiku 2 was nearly 742km long but took nearly 4 years to complete. Therefore, the Quang Trach – Pho Noi section with a length of 519km, construction time of only 7 months is LIGHTNING SPEED.

According to VTV Money.

Related article

“Miracle” of the electricity industry: 500KV line 3 completed in 7 months

Previously, the 500kV line 3 project from Vung Ang to Pleiku 2 was nearly 742km long but took nearly 4 years to complete. Therefore, the Quang Trach – Pho Noi section with a length of 519km, construction time of only 7 months is LIGHTNING SPEED.According to VTV Money.

A project that is considered a miracle of the new era in construction investment, a national key project of great significance for the development of the country. The 500kV line 3 project has been completed! Source: Vietnam Electricity

The sprint to achieve the goal of inauguration on the occasion of National Day, September 2, 2024, is taking place at the construction sites of the 500kV line 3, Quang Trach - Pho Noi section. The next 20 days are the time to promote the spirit of "only discussing work, not retreating", "overcoming the sun to win the rain, not losing to the wind and storm"...Prime Minister Pham Minh Chinh inspects, urges and encourages the implementation of the 500 kV power transmission line project, circuit 3, Quang Trach - Pho NoiMany seniors in the electricity industry, when mentioning the 500...

LIGHTNING CAMPAIGN – 500KV CIRCUIT 3 TRANSMISSION PROJECT

A project that is considered a miracle of the new era in construction investment, a national key project of great significance for the development of the country. The 500kV transmission line project, circuit 3, has been completed!Source: Vietnam Electricity

EVN: Determined to complete the 500kV Lao Cai - Vinh Yen transmission line project before September 2, 2025

EVN: Determined to complete the 500kV Lao Cai - Vinh Yen transmission line project before September 2, 2025On March 3, 2025 in Yen Bai, Vietnam Electricity Group (EVN), Power Project Management Board 1 held a ceremony to launch the construction of the 500kV Lao Cai - Vinh Yen transmission line, the section passing through Yen Bai province.EVN: Determined to complete the 500kV Lao Cai - Vinh Yen transmission line project before September 2, 2025Delegates attending the ceremonyAttending the construction launch ceremony were Mr. Ngo Hanh Phuc - Vice Chairman of Yen Bai Provincial People's Committee, Mr. Hoang Thi Thanh Binh...

Deploying the construction of the 500kV Lao Cai-Vinh Yen transmission line, the section passing through Yen Bai province

NDO – On March 3, in Yen Bai, Vietnam Electricity (EVN) and Power Project Management Board 1 held a ceremony to launch the construction of the 500kV Lao Cai-Vinh Yen transmission line, the section passing through Yen Bai province. This is one of the national key projects, of strategic significance in ensuring energy security and improving the operation capacity of the national power system.Delegates performed the ceremony to launch the construction of the 500kV Lao Cai-Vinh Yen transmission line, the section passing through Yen Bai province.Delegates performed the ceremony to launch the construction of the 500kV Lao Cai-Vinh Yen transmission...

Racing against time on the record high point of the 500kV line circuit 3

On the entire construction route of the 500kV line 3, positions 119, 120, 214 and 215 crossing the Red River and Luoc River are holding the "highest" record with a height of up to 145m. At the construction site, hundreds of officers and employees of Song Da 11 Joint Stock Company are urgently working hard, ready to work "3 shifts, 4 shifts" with the determination to bring the project to the finish line soon.Racing against timeNear noon, the sun was already harshly hanging on the top of the tens of meters high tower, sweltering, making the tower system at the...

Prime Minister: Going abroad, searching each container to bring equipment back to build the 500kV line

The Prime Minister requested to launch a special peak competition, "sprint", "lightning speed" to strive to basically finish erecting the 500kV line in June and complete the project in July.The Prime Minister inspected the 500kV line in Thanh Hoa and Nghe AnOn the morning of June 23, Prime Minister Pham Minh Chinh continued to inspect the site, urge and motivate the staff, workers, employees and chaired a meeting with relevant agencies on the implementation of the 500kV power transmission line project, circuit 3, Quang Trach - Pho Noi.Inspecting the construction of column 22 in Quynh Trang commune, Hoang Mai town,...

Song Da Corporation and Vietnam Construction Trade Union visited, encouraged and presented gifts to union members and workers who are constructing the 500KV Circuit 3 Transmission Line Project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) of Song Da 11 Joint Stock Company.

Implementing the 2024 working program of the Executive Committee of the Trade Union of Song Da 11 Joint Stock Company, continuing the series of activities to visit, encourage and give gifts to workers who are working at the 500KV Transmission Line Circuit 3 project, on August 7, 2024. The working delegation of Song Da Corporation and the Vietnam Construction Trade Union came to work, visit, encourage and give gifts to union members and workers of Song Da 11 Joint Stock Company who are working at the 500KV Transmission Line Project from Quang Trach (Quang Binh) to Phoi Noi (Hung Yen)...
logo

Song Da 11 Thang Long Company Limited

BT03 - VT24 - Xa La New Urban Area - Phuc La Ward - Ha Dong District - Hanoi City

Hotline: (024) 33554511, (024) 8588 7666

Email: songda11thanglong@gmail.com

About us

Shareholder

Copyright 2025 © DooTech